KITCHEN RENOVATION

 

Wednesday, July 25, 2018

Work has begun on the renovation of our multi-purpose room kitchen!  A team of 8 men began demolition of the kitchen today at 5:30AM. The contractor started by removing all the existing fixtures, the ceiling, and old mechanical systems. The new kitchen will have all new walls, ceiling, and floor. New heating, air conditioning, and ventilation systems and all new kitchen equipment will be installed. The project will take about two months, but with some luck, it will be done before school starts. In the meantime, pardon our mess.

 

Wednesday, August 1, 2018

Demolition is complete and so far there have been no surprises. Keep praying!

 

Friday, August 3, 2018

The metal wall studs are in. New electric and plumbing are in progress. The contractor hopes to have Montgomery County inspections for electric and plumbing completed next week.

 

Saturday, August 11, 2018

Most of this week’s work has been “behind the scenes.”  Plumbing has been rerouted, below-slab work has been done, and electrical lines have been run.

 

Friday, August 17, 2018

The new drywall went up where the hood will be installed.  The kitchen equipment is expected to start arriving next week.